Project Procedure and Time Specification in Building a Musical Dancing Fountain Project

06-03-2025

Project Procedure and Time Specification 

in Building a Musical Dancing Fountain Project


We are fountain expert Rainbows Fountain who offer turkey musical dancing water fountain projects in the whold word, we have the largest fountain factory in southern China, with over 20+ years overseas fountain project experience, Since the establishment of company, we have done landmark projects for 63+ countries, 4500+ projects.  Our target is turn every design into the actual unique fountain show and bring the best visual feast to our clients and audience. 


To help you better plan and manage your musical dancing fountain project timeline, we have detailed the general fountain process and approximate time specification requirements for collaborating with us on a dancing fountain project. By referring to the information below, you can estimate the time needed for each stage of your specific project, ensuring a more precise understanding of the overall construction schedule to make well-informed decisions.


1.Online Communication Client's Requirements on Dancing Fountain

  • After receiveing your inquiry, our professional sales will reply you immediately ( pls prepare requirements such as Fountain Site suituation, Fountain Size Fountain Type, Your Budget ect)

  • Time: 1hour to 1 Day to finish collect your requirements.

Dancing Fountain

2.Customized Unique Design on Musical Dancing Water Fountain

  • Free plan design with quoation: 1-3 working days

  • Free video clip effect: 1-3 working days

  • 3D animation video: 7-10 working days

  • Time period depeneds on project size and complexity

Musical Dancing Fountain

3. Production Of Dancing Fountian Equipments

  •  Generally fountain equipment production period need 10-30days.

  • If customized products according to such as 3phases 220V 60hz or single phase voltage, and if very huge projects such as Big O or floating projects, production need about 30-60days.

Fountain

4. Shipment Of Musical Dancing Fountain Equipment

  • Shipment time relys on project destination and the type of transportation selected. Air and sea shipping affect much on time.Once finished manufacturing and rigorous quality inspections, we will pack very well by wooden case for shipping.

  • Generally, the shipping process takes approximately 30 days.


Dancing Fountain

5. Installation Fountain Equipment On-Site

  • According to the actual circumstances of client's fountain project, we'll send our professional and experienced engineers to project site for installation,debugging, programming guidance and training.

  • Client side need also hire certain labors to assist, for a medium to large dancing fountain project, the period is around 25-50 days.

Musical Dancing Fountain